摘要
内蒙古大唐托克托发电厂三期工程主机冷却采用直接空冷系统,单机空冷系统由16棵直径4.2 m、高36.8 m的环形柱组成,针对工程独立性、重复性的特点,从施工班组、安全文明施工、施工机械、模板、脚手架、冬季施工等方面展开深入讨论,制定了科学的施工方案.通过在实践中的不断摸索,形成了成熟的施工方案.在工期紧张、气候恶劣的条件下,安全、优质地完成主体施工.
For the main engine cooling system of the third phase project of Datang Tuoketuo Power Plant in the Inner Mongolia Autonomous Region,the direct air-cooling system is adopted;and the single engine air-cooling system is constituted by 16 ring columns with 4.2 m diameter,36.8 m high.In light of some engineering structural features such as independence and repeatability,a scientific construction plan is performed after expansion discussion from construction teams,safety and civilized construction,contraction,ma...
出处
《武汉大学学报(工学版)》
CAS
CSCD
北大核心
2007年第S1期355-358,共4页
Engineering Journal of Wuhan University
关键词
空冷支柱
施工方案
经验
air-cooled pillar
construction scheme
experience