采用拓扑遍历方法优化船舶设计计划 被引量:4

Optimization on ship design planning by topological ergodicity
下载PDF
导出
摘要 为有效解决资源约束下的船舶设计多项目调度问题,根据船舶设计任务调度的特点,综合考虑船舶设计过程中各种影响因素和约束条件,以拓扑遍历方法为基础,提出了一种多项目调度问题的拓扑遍历优化算法。该算法具有对含耦合关系的项目进行处理的特点,在确定调度计划的过程中,提出以当前任务对后续任务的影响程度,以及关键路径任务优先的优先原则,并结合工程实例,验证了该算法的可行性。 To solve resource-constrained multiproject scheduling problem in ship design, a topological ergodicity optimization algorithm was presented, whose objective function was minimal duration. The algorithm was designed based on the topological ergodieity in view of the schedule characteristics, the influence factors and constraints in the process of ship design. Projects with coupled relation could be processed by the algorithm, in which the priority rules of schedule plan were critical path and the influence degree of late tasks by current task. An engineering instance verified the feasibility of this algorithm.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2007年第3期431-436,共6页 Computer Integrated Manufacturing Systems
基金 国家863/CIMS主题资助项目(2003AA414060)~~
关键词 产品开发计划 拓扑遍历 船舶设计 多项目调度 product developing plan topological ergodicity ship design multiproject scheluding
  • 相关文献

参考文献12

  • 1王爱虎,杨曼丽.复杂产品开发项目系统化管理方法[J].工业工程与管理,2005,10(3):7-16. 被引量:11
  • 2方炜,欧立雄.多项目环境下新产品研发项目资源分配问题研究[J].管理工程学报,2005,19(B10):6-10. 被引量:13
  • 3寿涌毅.资源约束下多项目调度的迭代算法[J].浙江大学学报(工学版),2004,38(8):1095-1099. 被引量:46
  • 4BRUCKER P,ANDREAS D,ROLF M,el at.Resource-constrained project scheduling:notation,classification,models,and methods[J].European Journal of Operation Research,1999,112(1):3-41.
  • 5KOLISCH R.Serial and parallel resource-constrained project scheduling methods revisited:theory and computation[J].European Journal of Operational Research,1996,90(2):320-333.
  • 6LOVA A,MAROTO C,TORMOSP.A multicriteria heuristic method to improve resource allocation in multiproject scheduling[J].European Journal of Operational Research,2000,127(2):408-424.
  • 7FENDLEY L G.Towards the development of a complete multiproject scheduling system[J].Journal of Industrial Engineering,1968,19(10):505-515.
  • 8KURTULUS I,DAVIS E W.Multi-project scheduling:categorization of heuristic rules performance[J].Management Science,1982,28(2):161-172.
  • 9DUMOND J,MABERT V A.Evaluating project scheduling and due date assignment procedures:an experimental analysis[J].Management Science,1998,34 (1):101-118.
  • 10STEWARD D V.The design structure system:a method for managing the design of complex system[J].IEEE Transactions on Engineering Management,1981,28 (3):71-74.

二级参考文献48

  • 1寿涌毅.资源约束下多项目调度的迭代算法[J].浙江大学学报(工学版),2004,38(8):1095-1099. 被引量:46
  • 2董明,查建中,郭伟.并行工程中的任务组织[J].系统工程理论与实践,1996,16(8):69-78. 被引量:34
  • 3TURNER J R. The handbook of project-Based management [M]. London: McGraw-Hill, 1993.
  • 4KURTULUS I, DAVIS E W. Multi-project scheduling:Categorization of heuristic rules performance[J]. Management Science, 1982, 28(2): 161 - 172.
  • 5TSAI D M, CHIU H N. Two heuristics for scheduling multiple projects with resource constraints [J]. Construction Management and Economics, 1996, 14:325 -340.
  • 6SPRECHER A, KOLISCH R, DREXL A. Semi-active,active, and non-delay schedules for the resource-constrained project scheduling problem[J]. European Journal of Operational Research, 1995, 80: 94 - 102.
  • 7LI K Y, WILLIS R J. An iterative scheduling technique for resource-constrained project scheduling[J]. European Journal of Operational Research, 1992, 56: 370-379.
  • 8OZDAMAR L, ULUSOY G. A note on an iterative forward/backward scheduling technique with reference to a procedure by Li and Willis [J]. European Journal of Operational Research, 1996, 89: 400- 407.
  • 9TORMOS P,LOVA A. An efficient multi-pass heuristic for project scheduling with constrained resources[J].International Journal of Production Research, 2003, 41(5):1071-1086.
  • 10SeligerG WeberH SchreterW 祁国宁 译.复杂产品开发中的协同工作[J].工程设计(Konstruktion),1999,(1):1013-1013.

共引文献64

同被引文献16

引证文献4

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部