摘要
对跨海大桥海滩处承台钢板桩围堰方案的设计及施工进行了研究,详细介绍了钢板桩的施工要点,有效缩短了工期,达到了结构合理,施工方便、安全高效的效果。
Combined with one cross-sea bridge works the design and construction of steel sheet pile cofferdam of platform in beach are introduced and studied. Key points for steel sheet pile construction are introduced in detail, which is reasonable and convenient with good effects in reducing limit time and ensuring construction safety.
出处
《山西建筑》
2007年第26期318-319,共2页
Shanxi Architecture
关键词
承台
钢板桩围堰
设计
施工
platform, steel sheet pile cofferdam, design, construction