LOT SIZING WITH NON-ZERO SETUP TIMES FOR REWORK 被引量:2

LOT SIZING WITH NON-ZERO SETUP TIMES FOR REWORK
原文传递
导出
摘要 In this paper we consider a single machine multi-product lot scheduling problem in which defective items are produced in any production run of each product. In each cycle after the normal production of each product the machine is setup for the rework of the defectives of the same product and then the rework process starts. We assume that the setup time for the normal production process as well as the rework process is non-zero. Further we consider the waiting time cost of defectives for rework. This paper has two objectives. The first objective is to obtain the economic batch quantity (EBQ) for a single product. The second objective is to extend the result of the first objective to the multi-product case. Adopting the common cycle scheduling policy we obtain optimal batch sizes for each product such that the total cost of the system per unit time is minimized. In this paper we consider a single machine multi-product lot scheduling problem in which defective items are produced in any production run of each product. In each cycle after the normal production of each product the machine is setup for the rework of the defectives of the same product and then the rework process starts. We assume that the setup time for the normal production process as well as the rework process is non-zero. Further we consider the waiting time cost of defectives for rework. This paper has two objectives. The first objective is to obtain the economic batch quantity (EBQ) for a single product. The second objective is to extend the result of the first objective to the multi-product case. Adopting the common cycle scheduling policy we obtain optimal batch sizes for each product such that the total cost of the system per unit time is minimized.
出处 《Journal of Systems Science and Systems Engineering》 SCIE EI CSCD 2008年第2期230-240,共11页 系统科学与系统工程学报(英文版)
关键词 Inventory control REWORK lot scheduling production control Inventory control, rework, lot scheduling, production control
  • 相关文献

参考文献22

  • 1[1]Cook,W.D.,Saipe,A.L.& Seiford,L.M.(1980).Production runs for multiple products:the full-capacity heuristic.Journal of Operations Research,31:405-412
  • 2[2]Dobson,G.(1987).The economic lotscheduling problem:achieving feasibility using time varying lot-sizes.Journal of Operations Research,35(5):764-771
  • 3[3]Elmaghraby,S.F.(1978).The economic lot scheduling problem (ELSP):review and extensions.Management Science,24(6):587-598
  • 4[4]Gallego,G.& Shaw,D.X.(1997).Complexity of the ELSP with general cyclic schedules.HE Transaction,29:109-113
  • 5[5]Glass,C.A.(1992).Feasibility of scheduling lot sizes of these products on one machine.Management Science,18(10):1482-1495
  • 6[6]Goyal,S.K.& Gonashekharan,A.(1990).Effect of dynamic process quality control on the economic production.International Journal of Operations and Production Management,10(3):69-77
  • 7[7]Graves,S.C.(1979).On the deterministic demand multi-product single machine for scheduling problem.Management Science,25:276-280
  • 8[8]Gunter,S.I.& Swanson,L.A.(1986).A heuristic for zero setup cost lot sizing and scheduling problems.In:ORSA-TIMS Conference,27-28,October 1986,Miami,Florida,USA
  • 9[9]Haessler,R.W.(1979).An improved extended basic period procedure for solving the economic lot scheduling problem.AIIE Transaction,11:336-340
  • 10[10]Haji,R.& Mansuri,M.(1995).Optimum common cycle for scheduling a single machine multi-product system with a budgetary constraint.Production Planning & Control,6(2):151-156

同被引文献8

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部