结合具体工程实例,介绍了双钓鱼法、工地运送梁及架梁的设备,详细地说明了30 m箱梁安装的施工工艺流程,指出双钓鱼法安装预制箱梁工艺具有施工成本低、安装速度慢、安全系数低等特点。
Combining with concrete engineering example, it introduces double fishing method, transporting beam in building site and equipment of erecting beam, detailed illustrates constructing craft process of 30 m box beam installation, it indicates that using double fishing method to install prefabricating box beam craft has some characteristics, low constructing cost, slow installing rate, low safe coefficient, etc.
出处
《山西建筑》
2008年第35期139-140,共2页
Shanxi Architecture
关键词
双钓鱼法
预制箱梁
安装
施工工艺
double fishing method, prefabricating box beam, install, constructing craft