摘要
沉沙池排沙廊道淤塞问题是很多水电站遇到的实际问题.针对印德拉瓦迪3号电站沉沙池排沙廊道淤塞,分析了其廊道淤塞的原因,并提出相应的解决办法,在后期运行中起到很好的效果.
The block of the sedimentation basin is the practical problems which is met in many hydropower stations.Aim at the block of the sediment corridor of the sedimentation basin,the block reason and the corresponding solution are proposed in this paper.The effect of later running is good.
出处
《江西水利科技》
2010年第3期167-169,共3页
Jiangxi Hydraulic Science & Technology
关键词
水电站
沉沙池
廊道淤塞
Hydropower station
Sedimentation basin
Corridor block