摘要 乌兰察布地区风电场并网发电,而地区电网建设滞后于风电场送出需求,出现限发、弃风等现象。以玫瑰营风电场为例,对风电场220 kV、110 kV、35 kV分布式接入方案进行技术条件、经济性比较,并结合乌兰察布地区局部电网实际,从潮流方向、电压质量和继电保护的影响等方面进行分析,确定了风电场最优接入系统方案:将该风电场分为3部分,分别接入35 kV乌拉哈变、五十号变、柏宝庄变变。分析结果证明,风电场分布式接入方案可有效缓解局部电网限发现象,为风电场接入方案的选择提供参考。 Many wind farms interconnected into the Wulanchabu regional power grid in recent years,the construction scale of the grid is lagging behind total installed increasing capacity of the wind farms,so the grid often limits wind power generation output,sometimes even prohibits the wind power generation.The paper determines that the optimal grid access scheme for the wind power plant is to be divided into three parts:each part of the plant respectively connected to the 35 kV Wulaha substation,35 kV Wushihao substation and Baibaozhuang substation.The results of studies prove that the distributed grid access scheme for wind farms can effectively alleviate restrictions on wind power of the local power grid which provide reference for the selection of the programmes of wind farm integrated into power grid.
作者 王海青
机构地区 乌兰察布电业局
出处 《内蒙古电力技术》 2012年第5期41-44,48,共5页 Inner Mongolia Electric Power
关键词 风电场 分布式接入方式 技术条件 潮流方向 SVC装置 wind farms distributed access methods technique conditions trend direction SVC device
  • 相关文献

参考文献3

  • 1李俊峰.风电12在中国[M].北京:化学工业出版社,2005:27-42.
  • 2雷亚洲.与风电并网相关的研究课题[J].电力系统自动化,2003,27(8):84-89. 被引量:457
  • 3全国电力监管标准化委员会.GB/T19963-2011风电场接入电力系统技术规定[S].北京:中国标准出版社,2011.

二级参考文献41

  • 1[1]Brown L. World Wind Generating Capacity Jumps 31 Percent in 2001. http://www.earth-policy.org
  • 2[2]Jenkins N. Embedded Generation (Part 2). Power Engineering Journal, 1996, 5: 233~239
  • 3[3]Feijoo A, Cidras J. Modeling of Wind Farms in the Load Flow Analysis. IEEE Trans on Power Systems, 2000, 15(1): 110~115
  • 4[4]Larsson A. Flicker Emission of Wind Turbines Caused by Switching Operation. IEEE Trans on Energy Conversion, 2002, 17(1): 119~123
  • 5[5]Larsson A. Flicker Emission of Wind Turbines During Continuous Operation. IEEE Trans on Energy Conversion, 2002, 17(1): 114~118
  • 6[6]IEC 1000-3-7. Assessment of Emission Limits for Fluctuating Loads in MV and HV Power Systems. 1996
  • 7[7]Bossanyi E, Saad-Saoud Z, Jenkins N. Prediction of Flicker Produced by Wind Turbines. Wind Energy, 1998, 1(1): 35~51
  • 8[8]Feijóo A, Cidrás J. Analysis of Mechanical Power Fluctuations in Asynchronous WECS. IEEE Trans on Energy Conversion, 1999, 14(3): 284~291
  • 9[9]Saad-Saoud Z, Jenkins N. Models for Predicting Flicker Induced by Large Wind Turbines. IEEE Trans on Energy Conversion, 1999, 14(3): 743~748
  • 10[10]Amaris H, Vilar C, Usaola J, et al. Frequency Domain Analysis of Flicker Produced by Wind Energy Conversions Systems. In: Proceedings of 8th International Conference on Harmonics and Quality of Power System, Vol 2. Athens (Greece): 1998. 1162~1167

共引文献456

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部