3-D numerical modelling of Domino failure of hard rock pillars in Fetr6 Chromite Mine, Iran, and comparison with empirical methods 被引量:11

3-D numerical modelling of Domino failure of hard rock pillars in Fetr6 Chromite Mine, Iran, and comparison with empirical methods
下载PDF
导出
摘要 Fetr6 is an underground mine using the stope-and-pillar mining method. As there was some evidence regarding pillar failure in this mine, improving works such as roof support and replacing existing pillars with concrete pillars (CP) were carried out. During the construction of the second CP, in the space between the remaining pillars, one of the pillars failed leading to the progressive failure of other pillars until 4 000 m 2 of mine had collapsed within a few minutes. In this work, this phenomenon is described by applying both numerical and empirical methods and the respective results are compared. The results of numerical modelling are found to be closer to the actual condition than those of the empirical method. Also, a width-to-height (W/H) ratio less than 1, an inadequate support system and the absence of a detailed program for pillar recovery are shown to be the most important causes of the Domino failure in this mine. Fetr6 is an underground mine using the stope-and-pillar mining method. As there was some evidence regarding pillar failure in this mine, improving works such as roof support and replacing existing pillars with concrete pillars (CP) were carried out. During the construction of the second CP, in the space between the remaining pillars, one of the pillars failed leading to the progressive failure of other pillars until 4 000 m2 of mine had collapsed within a few minutes. In this work, this phenomenon is described by applying both numerical and empirical methods and the respective results are compared. The results of numerical modelling are found to be closer to the actual condition than those of the empirical method. Also, a width-to-height (W/H) ratio less than 1, an inadequate support system and the absence of a detailed program for pillar recovery are shown to be the most important causes of the Domino failure in this mine.
出处 《Journal of Central South University》 SCIE EI CAS 2013年第2期541-549,共9页 中南大学学报(英文版)
关键词 hard rock Domino failure numerical modelling empirical method STOPE PILLAR extraction ratio W/H ratio Domino 数值模拟 支柱 3-D 铬矿 故障 伊朗 岩石
  • 相关文献

参考文献21

  • 1ZIPF R K. Toward pillar design to prevent collapse of room and pillar mines[R].NIOSH-Spokane Research Laboratory,2011.
  • 2SWANSON P L,BOLER F. The magnitude 5.3 seismic event and collapse of the solvay trona mine:Analysis of pillar/floor failure stability[U S Bureau of Mines OFR 86-95][R].1995.
  • 3ZIPF R K. Pillar design to prevent collapse of room-and-pillar mines[A].Littleton,CO,Society for Mining,Metallurgy,and Exploration,1982.
  • 4BRYAN A,BRYAN J G,FOUCHE J. Some problems of strata control and support in pillar workings[J].The Mining Engineer,1966.238-254.
  • 5SHEOREY P R,BARAT D,MUKHERJEE K P,PRASAD R K DAS M N BANERJEE G DAS K. Application of the yield pillar technique for successful depillaring under stiff strata[J].Int J of Rock Mech and Min Sci & Geomech,1995,(07):699-708.
  • 6GALVIN J. A review of coal pillar design in australia[A].Santa Fe:US Bureau of Mines Inform,1992.196-213.
  • 7ZIPF R K,SWANSON P L. Description of a Large Catastrophic Failure in a South western Wyoming Trona Mine,Paper in Rock Mechanics for Industry[A].Balkema,1999.293-298.
  • 8FARYAB COMPANY Ltd. Fetr-6 underground mine design,Technical report[R].2008.
  • 9BROWN E T. Rock characterization testing and monitoring,ISRM suggested methods[M].New York:pergaman Press,1981.
  • 10BIENIAWSKI Z T. Engineering Rock Mass Classification[M].New York:J.Willey,1989.