期刊文献+

金沙江巴塘水电站导流及主体工程分标方案分析 被引量:1

Analysis on Bidding Scheme for Diversion and Main Works of Batang Hydropower Station on Jinsha River
下载PDF
导出
摘要 水电站导流及主体工程分标是否合理,直接影响业主对资金的分配及管控,亦影响业主进度管理。分标方案划分与枢纽建筑物布置位置密切相关,枢纽建筑物分散布置与集中布置之分标方案有很大不同。以金沙江巴塘水电站为例,分析了建筑物集中布置之电站的分标方案,为以后类似工程的分标方案提供有益参考及借鉴。 Whether the bidding scheme for diversion and main works of the hydropower station is appropriate or not directly affects the owner's allocation and control of funds, and also affects the owner's progress management.The division of bidding section is closely related to the location of the complex structure.The bidding scheme for decentralized layout of complex structure is much different from that of the centralized layout.Taking the Batang Hydropower Station on Jinsha River as an example, the bidding scheme of the power station with centralized layout is analyzed, which provides useful reference for the bidding scheme of similar projects in the future.
作者 苏永江 周丹顺 贺威 SU Yongjiang;ZHOU Danshun;HE Wei(PowerChina Northwest Engineering Corporation Limited,Xi'an 710065,China)
出处 《西北水电》 2019年第3期49-52,共4页 Northwest Hydropower
关键词 导流 主体 分标 生态放水洞 巴塘水电站 diversion main works bidding scheme ecological drainage hole Batang Hydropower Station
  • 相关文献

参考文献14

二级参考文献63

共引文献46

同被引文献7

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部