摘要
糯扎渡水电站泄洪隧洞具有高水头、大泄量、高流速的特点,最大水头125.6m、最大泄量达3 395m^3/s、最高流速可达41m/s。高流速的泄洪隧洞常因空蚀而遭到破坏,介绍了糯扎渡水电站泄洪隧洞针对空蚀问题对泄洪洞体型、掺气减蚀措施、抗冲蚀混凝土材料、过流面不平整度控制等问题的研究与设计。
The tunnel spillways of Nuozhadu hydropower station is characterized by high head, large discharge and high flow velocity etc. The maximum head is 125.6 m, the maximum flood discharge is 3395 m^3/s and the maximum water velocity is 41 m/s. The cavitation damage in flood discharge tunnel of high flow velocity is common. The research and design of preventing cavitation damage in Nuozhadu's flood discharge tunnel, included the layout of tunnel, aeration mitigation, abrasion resistant concrete, flatness control, is presented briefly in this paper.
作者
郑大伟
冯业林
ZHENG Da-wei;FENG Ye-lin(Powerchina,Kunming Engineering Corporation Limited,Kunming 650051)
出处
《云南水力发电》
2019年第5期98-101,106,共5页
Yunnan Water Power
关键词
泄洪隧洞
空化空蚀
掺气减蚀措施
抗冲蚀混凝土材料
平整度控制
flood discharge tunnel
cavitation erosion
aeration mitigation
abrasion resistant concrete
flatness control