大跨度钢斜拉桥施工误差调整方法研究 被引量:3

Study on Construction Error Adjustment Method of Long-span Steel Cable-stayed Bridge
下载PDF
导出
摘要 针对斜拉桥施工中的线形、内力等施工误差,推导用最小二乘法对其进行调整的基本方程,提出考虑结构几何非线性的误差调整方法。结合某大跨度钢斜拉桥施工阶段的误差,给出其具体应用。 Long-span cable-stayed bridge is very popular in China. To improve the construction error of long-span cable-stayed bridge, such as configuration, internal force, the basic equations for error adjustment are deduced, using the least square method. And the construction error adjustment methods are put forward, considering the geometric non-linearity of the structure. Finally the least square method is used to adjust the construction error of a long-span steel cable-stayed bridge.
作者 郝超
出处 《公路交通科技》 CAS CSCD 北大核心 2003年第3期77-79,90,共4页 Journal of Highway and Transportation Research and Development
关键词 斜拉桥 施工误差 最小二乘法 误差调整 Cable-stayed Construction error Least square method Construction error adjustment
  • 相关文献

参考文献2

  • 1陈德伟.[D].上海:同济大学,1990-12.
  • 2崔冰,强士中,何畏.南京长江二桥南汉斜拉桥施工控制[C]//第十四届全国桥梁学术会议论文集.上海:同济大学出版社,2000:142-146.

共引文献2

同被引文献16

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部