资源约束项目计划关键序列与内在稳健性关系 被引量:3

Relationship between the Number of Critical Sequences and Intrinsic Robustness in Resource-constrained Project Schedules
下载PDF
导出
摘要 针对关键序列为决定项目计划内在稳健性的重要因素,采用Kolisch与Sprecher算例生成器Progen产生的算例j30rcp进行仿真试验以确定二者间的关系,并采用Tabachnik正态检验统计量和Wilcoxon检验统计量进行统计检验。结果表明,两种统计量的检验结果完全吻合,优化可控计划的稳健性优于非优化可控计划的内在稳健性,且资源链接越少、关键序列越少、项目计划的内在稳健性越优。 Critical sequence is an important factor for determination of intrinsic robustness of a project schedule.The relationship between critical sequence and project schedule is explored by simulation test of instance j30rcp,which is generated by Progen generator with Kolisch and Sprecher methods.Tabachnik normal and Wilcoxon tests are applied to statistical test at the same time.Simulation proves that the results obtained by two test statistics are consistent perfectly;an optimal controlled schedule is superior to a non-optimal controlled schedule for intrinsic robustness;fewer critical sequences and resource links mean better intrinsic robustness of a project schedule.
出处 《水电能源科学》 北大核心 2010年第7期127-129,共3页 Water Resources and Power
基金 中国博士后科学基金资助项目(20070420922) 国家自然科学基金资助项目(60574071) 广西壮族自治区教育厅科研基金资助项目(200712LX128) 广西民族大学引进人才科研启动基金资助项目(200702YZ01)
关键词 资源约束 项目计划 关键序列 稳健性 关系 Schedules 检验统计量 Wilcoxon检验 资源链接 重要因素 非优化 统计检验 检验结果 仿真试验 生成器 正态 resource constraints project schedule critical sequence intrinsic robustness extrinsic robustness
  • 相关文献

参考文献14

  • 1Van de Vonder Stijn,Demeulemeester Erik,Herro-elen Willy,et al.The Trade-off Between Stabilityand Makespan in Resource-constrained ProjectScheduling. International Journal of ProductionResearch . 2006
  • 2Przemyslaw Kobylański,,Dorota Kuchta.A Note on thePaper by M.A.Al-Fawzan and M.Haouari about a Bi-objective Problem for Robust Resource-constrained Pro-ject Scheduling. International Journal of ProductionEconomics . 2007
  • 3Hédi Chtourou,Mohamed Haouari.A two-stage-priori-ty-rule-based Algorithm for Robust Resource-constrainedProject Scheduling. Computers&Industrial Engi-neering . 2008
  • 4Cui Wanan,Wang Qianzhen,Cao Xiuning.LinksOptimization for Resource Constrained ProjectScheduling. 2008 International Conference onComputer Science and Software Engineering . 2008
  • 5Yang Kum-Khiong.A Comparison of Dispatching Rulesfor Executing a Resource-constraint Project with EstimatedActivity Durations. Omega . 1998
  • 6Barbara G Tabachnik,Linda S Fidell.Using MmultivariateStatistics. . 2006
  • 7Hartmann Sonke,Kolisch Rainer.Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem. European Journal of Operational Research . 2000
  • 8Al-Fawzan,M. A.,Haouari,M.A bi-objective model for robust resource-constrained project scheduling. International Journal of Production Economics . 2005
  • 9Goldratt EM.Critical Chain. . 1997
  • 10Wiest J. D.Some properties of schedules for large projects with limited resources. Operations Research . 1964

同被引文献40

  • 1崔万安,王先甲.资源约束项目计划内在稳健性度量方法[J].水电能源科学,2010,28(8):123-125. 被引量:2
  • 2卢纹岱.SPSS统计分析[M].北京:电子工业出版社,2012.
  • 3Wiest J. D. Some properties of schedules for large pro- jects with limited resources[J]. Operations Research, 1964,12(3) :395-418.
  • 4Stijn Van de Vonder, Erik Demeulemeester, Willy Her- roelen and Roel Leus. The trade-off between stability and makespan in resource-constrained project schedu ling[J]. International Journal of Production Research, 2006,44(2) :215-236.
  • 5Herroelen, Willy; De Reyck, Bert ; Demeulemeester, Erik, Resource-constrained project scheduling: A survey of re- cent developments[J]. Computers and Operations Re- search, 1998,25(4) : 279-302.
  • 6Brucker, Peter ; Drexl, Andreas ; M6hring, Rolf; Neu- mann, Klaus; Pesch, Erwin ; Resource-constrained pro- ject scheduling: Notation, classification, models, and methods [J]. European Journal of Operational Re- search, 1999,112(1) :3-41.
  • 7Hartmann, S6nke and Koliseh, Rainer, Experimental e- valuation of state-of-the-art heuristics for resource con- strained project scheduling[J]. European Journal for Operational Research, 2000 (127) : 394-407.
  • 8Kolisch,R and Padman, R, An integrated survey of de- terministic project scheduling[J]. Omega, 2001,29 ( 3 ) : 249-272.
  • 9Herroden,Willy; Demeulemeester, Erik; De Reyck, Bert, A note on the paper "Resource-constrained project schedu- ling: Notation, classification, models and methods" by Brucker et al[J]. European Journal of Operational Re- search, 2001,128(3) : 679-688.
  • 10M. A. A1-Fawzan and Mohamed Haouari. A bi-objective model for robust resource-constrained project scheduling[J]. International Journal of Production Economics, 2005, 96(2) : 175-187.

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部