新投产直接空冷机组汽水品质的控制 被引量:1

CONTROL OF STEAM-WATER QUALITY FOR THE DIRECT AIR COOLED UNIT HAVING BEEN NEWLY PUT INTO OPERATION
下载PDF
导出
摘要 新投产直接空冷机组普遍存在凝结水氢电导率、二氧化硅、铁等指标严重超标问题,致使给水、炉水、蒸汽等指标不合格,要靠锅炉大流量排污来维持汽水品质。为此,根据基建、调试和投运后3个不同阶段特点,分别提出了有针对性的措施,以确保新投产直接空冷机组汽水品质在较短时间内达到合格。 The problems of severely exceeding set standard for indices, such as hydrogen conductivety, silicon dioxide,and ferrous iron in condensate,are commonly existing in direct air cooled units having been newly put into operation,making the quality of feed water,boiler water,and steam etc to fall far from the required standards,hence,it is forced to increase the blowdown water from boilers for main- taining the quality of steam and water. For this,corresponding measures with clear aims have been put forward respectively on the basis of features in three different stages, namely capital construction,com- mission debugging,and after putting into operation,ensuring the quality of steam and water to be set standard in a short time.
出处 《热力发电》 CAS 北大核心 2009年第8期107-109,共3页 Thermal Power Generation
关键词 直接空冷机组 汽水品质 冷态冲洗 热态冲洗 凝结水 direct air- cooled unit quality of steam and water cold -state flushing hot- state flushing condensate
  • 相关文献

参考文献1

二级参考文献10

  • 1西安热工研究所.凝结水处理译文集(第2集)[R].1972.
  • 2国外水处理工作近况.电力译文,1973,(1):28-29.
  • 3陈永健.国外凝结水处理简介.电力技术通讯,1978,(2):11-11.
  • 4赴日考察实习报告(第7部分).电厂化学设计通讯,1980,(1):79-83.
  • 5张树芬.Powdex在我国应用的可能性.锅炉水处理,1986,(1):9-13.
  • 6大型电厂凝结水精处理赴美技术考察报告.水处理设备技术,1991,(4):29-32.
  • 7粉末树脂覆盖过滤器设备技术评审意见.电力设计水处理技术,1999,(4):54-55.
  • 8RobertKunin 金毅宏 等译.热力发电厂精处理用粉末树脂概述.电力设计水处理技术,1999,(4):22-24.
  • 9EliSalem TerranceLaTerra 韩买良译.五十年来凝结水精处理的发展.电力设计水处理技术,1999,(4):14-21,24.
  • 10韩(氵隶)传.粉末树脂覆盖过滤器的机理和使用[J].热力发电,2003,32(8):61-62. 被引量:19

共引文献9

同被引文献2

引证文献1

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部