Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix 被引量:4

Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix
原文传递
导出
摘要 Dependency Structure Matrix (DSM) is a successful and powerful tool for representing and analyzing dependencies between the items, but for external influencing factors it cannot charge effectively. This paper sets the stage for connecting the activities and resources, which not only considers information flow but also resources constrains.We first introduce the DSM to represent the degree of overlapping between the activities in a project. Then we present the Extended DSM combined former DSM and resource factors to calculate the project duration. Finally, the practical significance of the Extended DSM is confirmed by an illustrative example. Dependency Structure Matrix (DSM) is a successful and powerful tool for representing and analyzing dependencies between the items, but for external influencing factors it cannot charge effectively. This paper sets the stage for connecting the activities and resources, which not only considers information flow but also resources constrains.We first introduce the DSM to represent the degree of overlapping between the activities in a project. Then we present the Extended DSM combined former DSM and resource factors to calculate the project duration. Finally, the practical significance of the Extended DSM is confirmed by an illustrative example.
机构地区 School of Management
出处 《International Journal of Plant Engineering and Management》 2013年第4期204-211,共8页 国际设备工程与管理(英文版)
基金 supported by the National Natural Science Foundation of China under Grant No.71172123 the Aviation Science Fund under Grant No.2012ZG53083 the Soft Science Foundation of Shaanxi Province and the funds of NPU for Humanities and social sciences and management revilization under Grant No.RW201105
关键词 overlapped Extended DSM resource constraint project duration overlapped Extended DSM resource constraint project duration
  • 相关文献

参考文献11

  • 1Roy G,Nava P,Isrel S. Integrating system analysis and project management tools[J].International Journal of Project Management,2002.461-468.
  • 2Yassine A,Falkenburg D,Chelst K. Engineering design management:an information structure approach[J].Int J Prod Res,1999,(13):2957-2975.
  • 3Browning T R. Applying the design structure matrix to system decomposition and integration problems:a review and new directions[J].{H}IEEE Transactions on Engineering Management,2001.
  • 4Chen C,Ling S F,Chen W. Project scheduling for collaborative product development using DSM[J].International Journal of Project Management,2003,(21):291-299.
  • 5Guo Y T,Xu J C,Bai S J. Project scheduling with overlapping activities using dependency structure matrix[A].2007.1167-1172.
  • 6Eppinger S D,Whitney D E,Smith R P,Gebala D A. A modelbasedmethod for organizing task in product development[J].Des,1994,(1):13.
  • 7Browning T R. Use of dependency structure matrices for product development cycle time reduction[A].{H}Tokyo,Japan,1998.
  • 8Maheswari J Uma,Varghese K. Project scheduling using dependency structure matrix[J].International Journal of project Management,2005,(23):223-230.
  • 9Steward D V. Systems analysis and management:structure,strategyand design[M].Princeton:Petrocelli Books,1981.
  • 10Chen Chun-Hsien,Ling S F,Chen W. Project scheduling for collaborative product development using DSM[J].International Journal of Project Management,2003,(21):291-299.doi:10.1016/S0263-7863(02)00023-6.

同被引文献78

  • 1彭武良,王成恩.关键链项目调度模型及遗传算法求解[J].系统工程学报,2010,25(1):123-131. 被引量:33
  • 2刘晓峰,陈通,张连营.基于微粒群算法的工程项目质量、费用和工期综合优化[J].土木工程学报,2006,39(10):122-126. 被引量:40
  • 3SMITH-PERERA A,GARCIA-MELON M,POVEDA-BAUTISTA R,et al.A project strategic index proposal for portfolio selection in electrical company based on the analytic network process[J].Renewable and Sustainable Energy Reviews,2010(37):1569-15789.
  • 4CARAZO A F,GOMEZ T,MOLINA J,et al.Solving a comprehensive model for multiobjective project portfolio selection[J].Computers&Operations Research,2010(14):630-639.
  • 5SABATIER V,MANGEMATIN V,ROUSSELLE T.From recipe to dinner:business model portfolios in the European biopharmaceutical industry[J].Long Range Planning,2010(43):431-447.
  • 6MESKENDAHL S.The influence of business strategy on project portfolio management and its success—a conceptual framework[J].International Journal of Project Management,2010,28(8):807-817.
  • 7RIJKE J,VAN HERK S,ZEVENBERGEN C,et al.Adaptive programme management through a balanced performance/strategy oriented focus[J].International Journal of Project Management,2014,32(7):1197-1209.
  • 8TIKKANEN H,KUJALA J,ARTTO K.The marketing strategy of a project-based firm:the four portfolios framework[J].Industrial Marketing Management,2007,36(2):194-205.
  • 9PARTINGTON D,PELLEGRINELLI S,YOUNG M.Attributes and levels of programme management competence:an interpretive study[J].International Journal of Project Management,2005,23(2):87-95.
  • 10JIANMU Y,SHENBAO Y,JING Z.On reallocation of failed project resource based on priority[J].Systems Engineering Procedia,2012,4:338-344.

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部