摘要
针对高陡边坡加固防护中存在的施工难度大、施工周期长等困难,基于排水钉安装施工过程,改进了传统施工钻机、施工钻机平台,研制适用于既有铁路边坡加固的施工钻机及施工钻机平台,介绍改进后的施工钻机及施工钻机平台的具体构造。在此基础上,提出排水钉施工的一般规定,介绍排水钉施工时所需的技术准备、机具准备及工作条件,制定高陡边坡排水钉施工工艺流程,并提出相应的施工步骤和操作要求。
In view of the defects in high and steep slope reinforcement,such as great construction difficulty and long construction period,the traditional drilling rig and drilling rig platform were updated according to the installation and construction process of drainage nails.A drilling rig and drilling rig platform suitable for reinforcing the slopes of existing railways were developed.The specific structures of the updated drilling rig and drilling rig platform were outlined.On the basis of the updated drilling rig and drilling rig platform,general provisions on drainage nail construction were proposed,and technical preparations,machine preparations,and working conditions required for drainage nail construction were described as well.A process of drainage nail construction on high and steep slopes was formulated,and the corresponding construction steps and operation requirements were put forward.
作者
王风
聂如松
李锐
雷明峰
朱丽
牛建东
WANG Feng;NIE Rusong;LI Rui;LEI Mingfeng;ZHU Li;NIU Jiandong(Shuohuang Railway Development Co.,Ltd.,Cangzhou,Hebei 062350,China;School of Civil Engineering,Central South University,Changsha,Hunan 410075,China;MOE Key Laboratory of Engineering Structures of Heavy Haul Railway,Central South University,Changsha,Hunan 410075,China)
出处
《施工技术(中英文)》
CAS
2022年第14期126-133,共8页
Construction Technology
基金
国家自然科学基金(51878666)
朔黄铁路发展有限公司技术开发项目(SHTL-19-21)。
关键词
高陡边坡
施工钻机
施工钻机平台
排水钉
施工技术
high and steep slope
drilling rig
drilling rig platform
drainage nail
construction