摘要
坝基处理是土石坝施工的重要前提,高沥青混凝土心墙坝对坝基完整性、防渗级别提出了更高的要求,为了满足设计规范要求及加固坝基的目的,结合某高沥青混凝土心墙坝坝基灌浆施工技术实例,采用“固结灌浆→帷幕灌浆”坝基灌浆手段,克服了地质缺陷影响,达到了高沥青混凝土心墙坝坝基技术要求,提出高沥青混凝土心墙坝坝基处理的建议和展望。
Dam foundation treatment is an important precondition for earth-rock dam construction. High asphalt concrete core dam sets higher requirements for dam foundation integrity and seepage-proof level. In order to meet the requirements of design specifications and reinforce dam foundation, combined with the construction technology example of dam foundation grouting for a high asphalt concrete core wall, the dam foundation grouting method of "consolidation grouting curtain grouting" is adopted to overcome the influence of geological defects and meet the technical requirements of dam foundation for high asphalt concrete core wall. Suggestions and prospects for dam foundation treatment of high asphalt concrete core wall are put forward.
作者
林作章
王晨浩
LIN Zuo-zhang;WANG Chen-hao(YCIH No.1 Water Resources and Hydropower Construction Co.,Ltd.,Kunming 650599,China;Bei Fang Investigation,Design&Research CO.,LTD.,Tianjin 300222,China)
出处
《云南水力发电》
2023年第1期163-167,共5页
Yunnan Water Power
关键词
高心墙坝
沥青混凝土心墙
坝基灌浆
帷幕灌浆
high core dam
asphalt concrete core
dam foundation grouting
curtain grouting