地铁盾构下穿污水管的保护措施 被引量:1

Protection Measures for Shield Passing under the Sewage Pipes in Subway Engineering
下载PDF
导出
摘要 地铁工程建设不可避免下穿既有管线,为降低对既有管线的影响,保障盾构施工安全进行,以长春地铁6号线欧亚卖场站—光谷大街站区间隧道盾构施工下穿污水管为工程背景,对盾构掘进和预加固关键技术进行研究。从盾构掘进参数、出土量、袖阀管注浆、同步注浆、二次注浆和监测控制等方面进行施工技术控制分析,确保了工程的顺利完成。 Shield construction would inevitably pass under the existing pipelines.In order to reduce the construction-induced impact on existing pipelines and ensure the safe construction of the shield machine,this paper studies the key construction techniques regarding shield excavation and pre-reinforcement measures by taking the shield-driven running tunnel between Eurasian Store Station and Guanggu Avenue Station of Changchun Metro Line 6 as the background.It analyzes the construction control technology from the aspects of shield driving parameters,mucking volume,sleeve valve pipe grouting,synchronous grouting,secondary grouting and monitoring,which finally ensures the smooth completion of the Project.
作者 朱明 温超 秦林 ZHU Ming;WEN Chao;QIN Lin(Shanghai Civil Engineering Co.,Ltd.of CREC,Shanghai 201906)
出处 《现代隧道技术》 CSCD 北大核心 2022年第S02期208-213,共6页 Modern Tunnelling Technology
关键词 盾构 下穿污水管 掘进参数 袖阀管注浆 同步注浆 实时监测 Shield Passing under sewage pipe Driving parameters Sleeve valve pipe grouting Synchronous grouting Real-time monitoring
  • 相关文献

参考文献5

二级参考文献26

共引文献4

同被引文献10

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部