长江小直径浅覆土盾构隧道上覆土增厚技术 被引量:1

Overburden Thickening Technology of Small Diameter Shallow Overburden Shield Tunnel in Yangtze River
下载PDF
导出
摘要 上覆土对盾构施工的影响十分突出。以常熟电厂取水隧道盾构施工为研究背景,针对长江下游水域小直径盾构隧道上方覆土较薄的情况,通过对江底浅覆土中盾构机推进时的受力状态进行分析,利用理论计算的方法得出覆土的最小安全厚度,然后阐述了利用充填砂袋的方式分层对盾构机上方的土层进行增厚施工,最终使得盾构机顺利通过江低浅覆土区域。 The influence of overlying soil on shield construction is very prominent.This paper takes the shield construction of intake tunnel in Changshu Power Plant as the research background.Firstly,the force state of the riverbed shield machine during propulsion is analyzed.Then the minimum safe thickness of overlying soil is obtained by theoretical calculation method.Finally,the soil layer above the shield machine is thickened by filling sand bags,which makes the shield machine pass through the shallow overlying area of the river bottom smoothly.
作者 李涛 LI Tao(China Railway 14th Bureau Group 4th Engineering Co.Ltd.,Ji’nan,Shandong 250001,China)
出处 《施工技术》 CAS 2019年第S01期759-762,共4页 Construction Technology
关键词 隧道工程 小直径 浅覆土 盾构 增厚 tunnels small diameter shallow overburden shields thickening
  • 相关文献

参考文献7

二级参考文献50

共引文献60

同被引文献8

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部