摘要
大型核电主厂房跨度大、节点多、结构比较复杂,目前对主厂房的节点设计大多只考虑节点的受力情况,而忽略了主厂房各构件的制作、运输和安装的难易程度,通过对大跨度主厂房节点的优化设计方案探讨,使主厂房构件在保证原节点受力要求的前提下,降低了构件的施工难度、节约了运输和安装的成本。
At present,due to the large span,multiple nodes,and complex structure of the large nuclear power plant,most of the node designs of the main plant only consider the force of the node,while ignoring the difficulty of making,transporting and installing the components of the main plant.This paper discusses the optimal design scheme of the large-span main plant nodes,so that the main plant components can reduce the construction difficulty of the components and save the transportation and installation costs while ensuring the force requirements of the original nodes.
作者
杨兴旺
窦建伟
杜西河
王旭宾
YANG Xingwang;DOU Jianwei;DU Xihe;WANG Xubin(Shandong Luneng Guangda Steel Structure Co.,Ltd.,PowerChina Nuclear Engineering Co.,Ltd.,Jining 272000,China)
出处
《武汉大学学报(工学版)》
CAS
CSCD
北大核心
2021年第S01期157-161,共5页
Engineering Journal of Wuhan University
关键词
大型核电站
主厂房
节点优化
设计
large nuclear power plant
main plant
node optimization
design