期刊文献+

新建水厂工艺联调联试运行分析

Test run analysis of new water plant combination test operation
下载PDF
导出
摘要 GM水厂根据净水工艺设置、管线布局等实际情况制定了工艺联调联试方案,在不到2周时间实现水厂通水运营,达到了一次通水的目标,解决了光明新区夏季用水高峰期缺水问题。 According to the water purification process setting,pipeline layout and other practical conditions,GM water plant formulated the process alignment and test plan,realized the water supply operation of the water plant in less than two weeks,achieved the goal of water supply in one time,and solved the problem of water shortage during the peak water consumption in summer in guangming new district.
作者 刘锦荣 杨瑞利 刘永忠 连家赓 吴浩 Liu Jinrong;Yang Ruili;Liu Yongzhong;Lian Jiageng;Wu Hao(Shenzhen Shenshui Guangming Water Co.,Ltd.,Shenzhen 518107,China)
出处 《给水排水》 CSCD 北大核心 2020年第S01期238-239,244,共3页 Water & Wastewater Engineering
关键词 新建水厂 工艺调试 通水运营 联调联试 New water plant Process adjustment Operation Process alignment and test
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部