摘要
以某排水泵站EPC工程为例,选取经济、技术、管理以及社会等4大类风险,运用集对分析法分析评价各风险大小并排序。研究表明:技术风险最大,其次是管理风险,再次为社会风险,所遇的经济风险最小。在上述分析基础上,针对各种风险提出应对策略,为设计单位牵头的EPC水利工程控制履约过程中风险提供参考。
This paper takes the EPC project of a drainage pumping station as an example,selects and analyzes four kinds of risks including economy,technology,management and society by set pair analysis method.The results show that the technical risk is the largest risk,followed by the management risk,and then the social risk,the economic risk is the least risk.On the basis of the above analysis,puts forward the countermeasures for various risks,which can provide certain reference for the risk control in the process of EPC water conservancy project implementation led by the design unit.
作者
张吉祥
郭慧芳
ZHANG Jixiang;GUO Huifang(Zhejiang Design Institute of Water Conservancy&Hydro-Electric Power,Hangzhou 31002,China;Zhejiang Tongji Science and Technology Vocational College,Hangzhou 311231,China)
出处
《建筑经济》
北大核心
2020年第S02期136-139,共4页
Construction Economy