摘要 文中以吴川市环保热力发电厂及配套设施项目为研究对象,分析发电厂土建的复杂地质现象,基于复杂场地情况,运用预应力高强度混凝土管桩作为土建基础,通过经验参数法计算出预应力高强度混凝土管桩的单桩竖向承载力。结果表明,本次试桩结果可为工程桩的设计与施工提供指导,确定沉桩时的停锤标准。 This paper takes Wuchuan environmental protection thermal power plant and supporting facilities project as the research object;Based on the complex geological phenomena of power plant construction,the vertical bearing capacity of prestressed high-strength concrete pipe pile is calculated by empirical parameter method.The results indicate that the test results can provide guidance for the design and construction of engineering piles,and determine the standard of stopping hammer during pile sinking.
作者 葛黄祥 Ge Huangxiang(Fujian Province Industrial Equipment Installation Co.Ltd.,Fuzhou,Fujian 350001)
出处 《江西建材》 2023年第8期283-284,287,共3页 Jiangxi Building Materials
关键词 场地复杂性 土建施工 发电厂 单桩竖向承载力 Site complexity Civil construction Power plants Vertical bearing capacity of single pile
  • 相关文献

参考文献6

二级参考文献32

共引文献20

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部