补连塔选煤厂重介质渣浆泵密封方式优化及应用 被引量:1

Optimization and application of sealing mode of heavy slurry pump in Bulianta Coal Preparation Plant
下载PDF
导出
摘要 为了延长重介离心泵使用周期、降低突发故障率,研究了补连塔选煤厂重介离心泵轴承组件、轴套损伤快的原因。基于单因素解决方案,提出了补连塔选煤厂重介离心泵密封方式优化方案。结果表明,采用橡胶骨架唇形密封方式优化方案,密封效果良好,设备运行稳定,泵组件及轴套使用周期由原来6个月延长至36个月,大大降低了维修费用,每年节约成本316.17万元。 In order to prolong the service life of the heavy-medium centrifugal pump and reduce the sudden failure rate,the causes of rapid damage to the bearing components and shaft sleeves of the heavy-medium centrifugal pump at Bulianta Coal Preparation Plant were studied.Based on the single-factor solution of the existing problems,an optimization scheme for the sealing method of the dense-medium centrifugal pump at Bulianta Coal Preparation Plant was proposed.The results show that the use of the rubber skeleton lip-shaped sealing method to optimize the plan,the sealing effect is good,the equipment operation process is stable,the pump components and the shaft sleeve use cycle is extended from the original 6 months to 36 months,which greatly reduces the maintenance cost and saves every year.The cost is 3161700 yuan.
作者 田娜 白刘贵 何永彬 TIAN Na;BAI Liugui;HE Yongbin(Bulianta Coal Preparation Plant,CHN Energy Shendong Coal Preparation Center,Ordos 017209,China)
出处 《洁净煤技术》 CAS 北大核心 2021年第S01期89-92,共4页 Clean Coal Technology
关键词 离心泵 轴承组件 密封 使用周期 成本 优化改造 centrifugal pump bearing assembly seal life cycle cost optimization
  • 相关文献

参考文献10

二级参考文献26

共引文献23

同被引文献6

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部