期刊文献+

变截面单箱双室连续刚构特大桥施工技术研究 被引量:1

Research on construction technology of continuous rigid frame large bridge with variable section single box and two chambers
下载PDF
导出
摘要 乌鲁木齐绕城高速公路(西线)工程为双向八车道公路,是我国西部高速公路网的重要组成部分,主线长93.616km,设计时速100km/h。其中,头屯河连接线特大桥为乌鲁木齐绕城高速公路(西线)工程的三座特大桥之一。头屯河连接线特大桥分为主桥、东引桥和西引桥三部分:西引桥上部结构为预制小箱梁,共5联,桥跨布置4×(3×40)+4×40m。东引桥上部结构为钢-混组合梁,共5联,桥跨布置4×(3×60)+3×45m。头屯河连接线特大桥主桥为本项目控制性工程,连续刚构梁体为单箱双室,变高度、变截面结构,采用菱形挂篮悬臂现浇法施工。上部结构连续刚构0#块采用托架施工,分两次浇筑成形。墩身预埋插销盒,通过安装牛腿托架作为0#块支撑体系,牛腿托架采用三角形托架,在横桥向两侧,每侧安装6片三角形托架,托架组合成为0#块施工支架受力系统,保证施工安全要求。连续刚构梁1~16节段采用菱形挂篮施工,0#块施工完成后,拼装挂篮,在挂篮底板采用预制块完成菱形挂篮预压,采集预压相关数据作为后期施工参考依据。悬臂两端节段同时施工,保持悬臂对称平衡,直至第16节段施工完成。 The main line of Urumqi Ring Expressway(West Line)project is 93.616 kilometers long,designed according to the standard of two-way eight-lane expressway,the design speed is 100km/h,and the width of the roadbed is 41m.Among them,the Tou Tunhe connection super bridge is one of the three super Bridges of Urumqi Ring Expressway(West Line)project.The super bridge is divided into three parts:the main bridge,the east approach bridge and the West approach bridge:the upper structure of the west approach bridge is prefabricated small box girder,a total of 5 pairs,and the bridge span arrangement is 4×(3×40)+4×40m.The upper structure of the east approach bridge is composed of steel-mixed composite beams with a total of 5 connections,and the bridge span arrangement is 4×(3×60)+3×45m.The main bridge of Toutun River connecting line is the control project of this project.The continuous rigid frame beam body is single box and double chamber,and the structure is variable height and cross-section.It is constructed by rhomboid hanging basket cantilever cast-in-place method.The continuous rigid frame 0#block of the superstructure is constructed by bracket and is divided into two pours.Pier embedded bolt box,through the installation of the bull leg bracket as a 0#block support system,the bull leg bracket uses a triangle bracket,on both sides of the cross bridge,each side of the installation of 6 pieces of triangle bracket,bracket combination into a 0#block construction bracket stress system to ensure construction safety requirements.Diamond-shaped hanging basket is used for the construction of 1-16 sections of continuous rigid frame beams.After the completion of the construction of 0#blocks,the hanging basket is assembled,and prepressure of diamond shaped hanging basket is completed by prefabricated blocks on the bottom plate of the hanging basket.The relevant data of prepressure is collected as a reference basis for later construction.The two end sections of the cantilever are constructed at the same time to maintain the symmetrical balance of the cantilever until the construction of section 16 is completed.
作者 侯圆 薛超 谢晶 张丹 HOU Yuan;XUE Chao;XIE Jing;ZHANG Dan(China Power Construction Road and Bridge Group Co.,Ltd.,Urumqi 830000,China;Hebei University of Technology,Tianjin 300401,China)
出处 《建筑结构》 北大核心 2023年第S02期1991-1996,共6页 Building Structure
关键词 高速公路 变截面 单箱双室 连续刚构桥 特大桥 施工技术 highway variable cross-section single box and two chambers continuous rigid frame bridge large bridge construction technology
  • 相关文献

参考文献9

二级参考文献44

  • 1虞建成,龚科,王东阳.某刚构-连续组合箱梁桥非设计合龙温度下合龙技术[J].施工技术,2006,35(8):84-86. 被引量:2
  • 2刘曰飞,许长青,阴晓云.大跨度连续刚构桥合龙应注意的几个问题[J].铁道建筑,2007,47(1):14-15. 被引量:9
  • 3.GB50017-2003钢结构设计规范[S].北京:中国计划出版社,2003..
  • 4JTJ025-86.公路桥涵钢结构及木结构设计规范[S].[S].北京,1988..
  • 5GB50205-2001,钢结构工程施工质量验收规范[S].北京:中国建筑工业出版社,2001.
  • 6张继尧,王昌将.悬灌浇注预应力混凝土连续梁桥[M].北京:人民交通出版社,2004.
  • 7JTG/TF50-2011,公路桥涵施工技术规范[S].
  • 8中交第一公路工程局有限公司.JTG/TF50-2011公路桥涵施工技术规范[S].北京:人民交通出版社,2011.
  • 9赵国堂,李化建.高速铁路高性能混凝土应用管理技术[M].北京:中国铁道出版社,2008:191-192.
  • 10TB10203-2002.铁路桥涵施工规范[S].[S].,..

共引文献73

同被引文献8

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部