摘要
结合实际工程-贵州饭店和贵阳市六广门污水处理厂,对高抗浮水位条件下岩石地基上超深超长地下结构的裂缝控制进行了理论计算与分析,论述了其裂缝控制要点。通过采用优化设计后的防水滑移层以及可释放水平刚度的抗浮锚杆,释放地基水平约束,结合温度控制及补偿收缩混凝土的应用等措施,达到构裂缝控制预期目标,为今后岩石地基上超深超长地下结构的裂缝控制设计提供借鉴及参考。
Combining with the actual project-Guizhou hotel and Guiyang Liuguangmen Sewage Treatment Plant,this paper theoretically calculates and analyzes the cracking control of the ultra-deep and ultra-long underground structure on the rock foundation under the condition of high anti-floating water level,discusses the key points of cracking control.By adopting the optimized waterproof sliding layer and the anti-floating anchor that can release the horizontal stiffness,releasing the horizontal constraint of the foundation,combining with the measures of temperature control and the application of shrinkage-compensating concrete,the expected goal of structural crack control is achieved,providing reference for the cracking control design of ultra-deep and ultra-long underground structures on rock foundation in the future.
作者
赖庆文
邓曦
王星星
夏恩德
王文彬
杨通文
莫大霖
林如锴
LAI Qingwen;DENG Xi;WANG Xingxing;XIA Ende;WANG Wenbing;YANG Tongwen;MO Dalin;LIN Rukai(Guizhou Architectural Design&Research Institute Co.,Ltd.,Guiyang 550081,China)
出处
《建筑结构》
北大核心
2023年第S02期1261-1266,共6页
Building Structure
关键词
裂缝控制
岩石地基
温度应力
抗浮锚杆
滑移层
cracking control
rock foundation
temperature stress
anti-floating anchor
sliding layer