摘要 顶推施工技术在桥梁工程应用中,对跨线、跨河区域交通影响小,具有吊装施工无法替代的优势,在我国桥梁工程中应用较为广泛,尤其是钢箱梁桥顶推施工居多。结合实际工程案例,采用2017MIDAS/Civil对支架及钢箱梁进行建模分析,对步履式多点顶推施工过程进行技术分析和探讨。 In the application of bridge engineering, the jacking construction technology has little impact on the traffic of the cross-line and river-crossing areas, and has the advantage that hoisting construction cannot be replaced. It is widely used in bridge engineering in my country, especially the steel box girder bridge jacking construction mostly. Combined with actual engineering cases, the 2017MIDAS/Civil is used to model and analyze the support and steel box girder, and the technical analysis and discussion of the walking multi-point push construction process are carried out.
作者 曹广飞 申岩 焦仲伟 李洪亮 刘江江 韩明涛 王方骏 CAO Guangfei;SHEN Yan;JIAO Zhongwei;LI Hongliang;LIU Jiangjiang;HAN Mingtao;WANG Fangjun(The Fourth Construction Co.,Ltd.of CSCEC 7th Division,Xi’an 710016,China)
出处 《建筑结构》 CSCD 北大核心 2022年第S02期2797-2801,共5页 Building Structure
关键词 钢箱梁 顶推施工 步履机 步履机电气控制系统 施工控制 steel box girder jacking construction walking machine electric control system of walking machine construction control
  • 相关文献

参考文献5

二级参考文献9

共引文献25

同被引文献43

引证文献8

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部