管线穿越不均匀结构沉降缝的施工技术和控制方法 被引量:2

Construction technology and control method of pipeline crossing settlement joint of uneven structure
下载PDF
导出
摘要 北京市南水北调郭公庄水厂工程,水厂炭吸附池系列建筑因受到施工用地紧张,各构筑物之间间隔较小,构筑物之间的沉降缝两侧存在不均匀沉降。在该工程穿墙管道的设计中,既要考虑穿墙管与墙体之间的防渗问题,又要考虑沉降缝两侧的不均匀沉降对管道造成的变形影响。本文依托该工程,提出了一种管线穿越不均匀结构沉降缝的施工技术和控制方法,解决了因不均匀沉降造成水工构筑物破坏及管道变形问题,实现了降低因不均匀沉降造成跨越沉降缝的工艺管道变形及水工构筑物破坏风险,为今后类似工程提供经验借鉴。 In Guogongzhuang waterworks project of Beijing south to north Water Diversion Project, due to the shortage of construction land, the space between the structures is small, and there is uneven settlement on both sides of the settlement joint between the structures. In the design of the through wall pipeline of the project, not only the anti-seepage problem between the through wall pipe and the wall should be considered, but also the influence of the uneven settlement on both sides of the settlement joint on the deformation of the pipeline should be considered. Based on the project, this paper puts forward a kind of construction technology and control method of pipeline crossing uneven structure settlement joint, solves the problems of hydraulic structure damage and pipeline deformation caused by uneven settlement. It also can reduce the risk of pipeline deformation and hydraulic structure damage caused by uneven settlement, and provide experience for similar projects in the future.
作者 刘明华 孟庆龙 杨光昌 LIU Minghua;MENG Qinglong;YANG Guangchang(Beijing Municipal Construction Group Co.,Ltd.,Beijing 100089,China;Department of Civil Engineering,University of Scienceand Technology Beijing,Beijing 100083,China)
出处 《建筑结构》 CSCD 北大核心 2021年第S02期1849-1853,共5页 Building Structure
关键词 不均匀沉降 管道 沉降缝 施工技术 uneven settlement pipeline settlement joint construction technology
  • 相关文献

参考文献8

二级参考文献34

共引文献28

同被引文献8

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部