摘要
随着城市化进程的加快,城市人口不断聚集,国内大多数城市选择新建污水厂以处理渐增的生活污水。而现状污水管持续高水位运行,因此新建污水厂与现状污水管道的接驳成为一大难题;常规手段为现状污水管直接停水进行接驳,但弊端明显。以深圳市埔地吓水质净化厂(三期)进厂管道成功不停水接驳实例切入,探析如何巧妙利用现有条件与设施实现不停水接驳。
With the acceleration of the urbanization process,the urban population continues to gather,and most cities in China choose to build sewage plants to deal with the increasing domestic sewage.However,the existing sewage pipes always run at high water levels,and the connection between the new sewage plant and the existing sewage pipeline has become a big problem.The conventional method is to stop the existing sewage pipes from running,but the disadvantages are obvious.The example of the successful uninterrupted water connection of the incoming pipelines of Pu Dixia sewage treatment plant(Phase III)is analyzed,and how to make use of the existing conditions and facilities to realize the uninterrupted water connection.
作者
甄万顺
张子鹏
项立新
周佳儒
无
Zhen Wanshun;Zhang Zipeng;Xiang Lixin;Zhou Jiaru;无(Powerchina Huadong Engineering Co.,Ltd,Hangzhou 311122,China;Shenzhen Weilan Design Consulting Engineering Co.,Ltd,Shenzhen 518107,China;Huadong Eco-Environmental Engineering Research Institute of Zhejiang Province,Hangzhou 311122,China;Power China Huadong Engineering(Shenzhen)Co.,Ltd,Shenzhen 518100,China)
出处
《环境工程》
CAS
CSCD
北大核心
2023年第S01期72-74,共3页
Environmental Engineering
关键词
不停水接驳
污水处理厂
污水管道
大口径管道
现状改造
uninterrupted water connection
sewage treatment plant
sewer pipeline
large diameter pipeline
status quo of the reform