海上风电变径钢管桩送桩器开裂机理与解决方案

Cracking Mechanism and Solution of Pipe Pile Feeder with Variable Diameter for Offshore Wind Power
下载PDF
导出
摘要 为彻底解决海上风电沉桩过程中送桩器开裂的问题,通过分析可能造成送桩器开裂的各种因素,确定送桩器在摇晃沉桩过程受剪力的关键因素,并据此制定了解决方案。结果表明,通过控制送桩器桩身和定位架导向筒、送桩器插尖和钢管桩的间隙可减少送桩器在施工过程中的晃动,降低开裂几率。为海上风电送桩器制作提供参考,也为变径钢管桩沉桩中送桩器产生开裂后提供解决方案。 In order to completely solve the problem of pile feeder cracking in the process of pile driving in offshore wind power,Analyzing various factors that may cause the pile feeder cracking,the key factors of the shear force in the process of pile driving are determined,and the solution is worked out.The results show that the sloshing of pile feeder and the rate of cracking can be reduced by controlling the clearance between pile body of pile feeder and guide cylinder of locating frame,the tip of pile feeder and steel pipe pile also to.It provides a reference for the manufacture of offshore wind power pile feeder,and also provides a solution for cracking of pile feeder in variable diameter steel pipe of pile driving process.
作者 刘子聃 吴剑明 冯金杰 汤丽娜 LIU Zidan;WU Jianming;FENG Jinjie;TANG Lina(Guangzhou Salvage Co.,Ltd.,Guangzhou 510290,China;CSSC Huangpu Wenchong Shipbuilding Co.,Ltd.,Guangzhou 510715,China)
出处 《船舶工程》 CSCD 北大核心 2024年第S01期494-499,共6页 Ship Engineering
关键词 送桩器 开裂 解决方案 the pile feeder cracks solutions
  • 相关文献

参考文献7

二级参考文献15

共引文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部