超长、超宽、超高构件双机抬吊技术应用

Technical Application of Superlong、Superwide、Superhigh Components that be Raised and Suspended by Double Machines
下载PDF
导出
摘要 大型构件吊装是一项风险性较强的施工技术,焦化干熄焦工程在原方案300t履带吊无法落实的情况下,通过一系列计算,以两台大型汽车吊代替300t履带吊,成功安装超长、超宽、超高构件,取得了良好的经济效益和社会效益。 The supermodel components of suspending and loading is a constrction technique which has more risk.The Coking-Dry-Burnt project in a situation that the original scheme 300t track not to be hung,through a series of calculates,substitute 300t track with two large-scale cranes to hang.Superlong superwide and superhigh components was succeeded in fixing.And more economic and social benefits were gained.
作者 吴川
出处 《安徽冶金科技职业学院学报》 2007年第4期41-42,46,共3页 Journal of Anhui Vocational College of Metallurgy and Technology
关键词 大型构件 双机抬吊 安装技术 Large-scale component,Dual machines are lifted and hung,Mounting technique