摘要
大型构件吊装是一项风险性较强的施工技术,焦化干熄焦工程在原方案300t履带吊无法落实的情况下,通过一系列计算,以两台大型汽车吊代替300t履带吊,成功安装超长、超宽、超高构件,取得了良好的经济效益和社会效益。
The supermodel components of suspending and loading is a constrction technique which has more risk.The Coking-Dry-Burnt project in a situation that the original scheme 300t track not to be hung,through a series of calculates,substitute 300t track with two large-scale cranes to hang.Superlong superwide and superhigh components was succeeded in fixing.And more economic and social benefits were gained.
出处
《安徽冶金科技职业学院学报》
2007年第4期41-42,46,共3页
Journal of Anhui Vocational College of Metallurgy and Technology
关键词
大型构件
双机抬吊
安装技术
Large-scale component,Dual machines are lifted and hung,Mounting technique