本文对利用“天梁抬吊荷载转移法”将厂房个别重型排架柱拆除,并换上托架梁支承屋架荷载的施工实例进行总结,以为类似工程之参考。
This article concludes an effective approach in a practical project of transferring the pillars. First step, it is to lift the beam with the crane and remove the load. And then it is supposed to replace heavy pillar with frame.
出处
《福建建筑》
2005年第Z1期320-251,共2页
Fujian Architecture & Construction
关键词
荷载转移
天梁抬吊
托梁拆柱
短柱顶撑
load transfer lift beam with crane support beam and remove pillar support by short pillar