在对高井热电厂100 MW汽轮机进行DEH改造的实践基础上,讨论了这次改造的方案特点,并介绍了改造过程。总结了改造中的经验,并提出了一些合理的解决方案和建议。
Based on the practice to transform 100 MW steam turbine with DEH technology,this paper discusses the characteristics of the plan of the transformation,and introduces the process of the transformation.The experiences of the transformation are summarized,and several appropriate solutions as well as propositions are put forward.
出处
《华北电力技术》
CAS
2007年第3期21-23,27,共4页
North China Electric Power
关键词
汽轮机
调速系统
DEH改造
steam turbine
governing system
DEH trasformation