摘要
厂区管线设施按常规流程设计,已不能满足电厂建设文明施工的要求,根据火力发电厂的工艺管线种类以及布置要求,从设计流程入手,对300 MW和600 MW机组的管线设施布置进行研究,提出厂区管线设施规划布置的接口及设计的具体要求,以达到指导工艺设计、细化施工设计、满足现场施工提前出图的目的.
Arranging the plant pipelines facility according to traditional process design can not meet the demand of civilization construction of power plants.In light of sorts and arrangement demand of the process of pipelines of thermal power plants;beginning with the design process,a lot of researches on the pipeline facility arrangement of 300 MW and 600 MW sets are carried out;some specific requirements of planned joints and design of the plant pipelines facility are proposed so as to guide the technological desi...
出处
《武汉大学学报(工学版)》
CAS
CSCD
北大核心
2007年第S1期72-75,共4页
Engineering Journal of Wuhan University
关键词
文明施工
管线布置
火电厂
civilization construction
pipeline arrangement
thermal power plant