摘要 介绍了内蒙古准能矸电有限责任公司150 MW机组调试过程中出现的启动时高压上下缸温差偏大、高中压缸胀差不易控制、汽封系统机组润滑油压力异常变化、机组异常振动、高压排汽逆止门前无泄放管路、挂闸后高压主蒸汽门不能全开等典型问题的现象、原因及处理方法,可供同类型机组启动调试时参考。 This paper expounds the phenomena,causes and treatment on typical problems while debugging in the 150 MW unit of Inner Mongolia Zhunnenggan Electric Power Co.Ltd.,in terms of the large temperature difference between the above and below cylinder in the high pressure cylinder during startup,be difficult to control on expansive difference of high and middle pressure cylinder,pressure exceptional changes of lubricating oil for steam seal system,exceptional vibration of unit,no leakage tube before high pressure exhaust check valves,not-full opening of high pre-ssure main steam door after closing the door.It should take references for the same type unit during debugging.
出处 《河北电力技术》 2007年第2期5-8,31,共5页 Hebei Electric Power
关键词 汽轮机 机组调试 温差 汽封 turbine unit debugging temperature differences steam seal gland steam seal
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部