摘要
通过首秦4300mm宽厚板工程实践,针对精轧机BOX箱型基础特点研究,应用后浇段施工技术替代现行使用的跳仓施工方法,取得了工程质量好,成本低,工期短的效果。
Through the practice of the 4 300mm Plate Mill Production Line project in Shouqin Metal Materials Co.,Ltd and the research on the BOX foundation of finishing mill,it applies the post-casting strap technology on construction instead of current separating spacing method so as to fulfill the effect:great quality,low cost and short construction time.
出处
《工业建筑》
CSCD
北大核心
2007年第z1期1074-1076,1089,共4页
Industrial Construction
关键词
箱型基础
后浇段法
跳仓法
施工缝
施工成本
BOX foundation post-casting strap method separate spacing method construction gap construction cost