摘要
三峡工程混凝土总量约2 800万m3,其中Ⅰ&ⅡB标段主要包括泄洪坝段和左厂10#~14#坝段,混凝土量为776.56万m3,占二期工程混凝土总量1 846万m3的42%,Ⅰ&ⅡB标段从1999年开始混凝土浇筑,至今累计完成600万m3。泄洪坝段混凝土施工直接关系到三峡工程总进度。
Out of a total concrete volume of some 28 million m3 at the Three Gorges project, 7 765 600 m3 concrete accounting for 42% of a total volume of 18.46 million m3 for the second - phase works, will be poured into the works Contract Nos. Ⅰ & ⅡB including mainly the spillway section and blocks Nos. 10 - 14 of the left powerhouse section. Since 1999, 6 million m3 concrete has been placed at the works Contact Nos. Ⅰ & ⅡB. The concrete construction at the spillway section has a direct impact on the master sche...
作者
邢德勇
胡少华
XING De - yong(TGP Construction Headquarters; China Gezhouba Construction Group; Yichang 443113. China);
出处
《中国三峡建设》
2001年第11期-,共3页
China Three Gorges Construction
关键词
三峡工程
泄洪坝段
混凝土
施工
质量控制
Three Gorges project (TGP)
spillway
concrete
construction
quality control.