摘要
针对宝钢四号高炉炉体快速安装工程的实际,在提升重量大、安装时间紧的情况下,为保证施工安全,提高工作效率,对提升框架进行了应力应变跟踪检测,解决了大型构件应力应变检测的一些关键技术。
According to the fact that the Baosteel 4BF shall be fast installed and in the case of the heavy lifting load and short installation time,in order to guarantee the construction security and improve working efficiency,the lifting component′s stress and stain were tracked and some key techniques in allusion to the detection of the large-scale component were solved.
出处
《工业建筑》
CSCD
北大核心
2006年第z1期926-928,947,共4页
Industrial Construction
关键词
大型构件
应力
应变
检测
large-scale component stress strain testing