摘要
长城矿业公司基建副立井出现了严重的井壁破坏,造成井筒建设停产。通过分析,认为井筒通过7号煤小窑采空区是井筒破坏的主要原因。为此有针对性地实施了"密集井圈+卸压槽+壁后注浆+锚杆加固"为主的抢险工程,井筒目前正常提升,取得了良好的治理效果,并且丰富了井壁破坏治理措施。
There was serious mine shaft liner failure occurred in the mine shaft construction period of the mine auxiliary mine in Changcheng Coal Mining Company and the shaft liner failure caused a pause to the mine shaft construction. After the analysis, the paper held that when the mine shaft sinking through a goaf in No. 7 seam of a small mine was the main cause of the mine shaft failure. Therefore, an emergency repair project with the intensive shaft ring, strata pressure releasing slot, shaft liner back grouting...
出处
《煤炭科学技术》
CAS
北大核心
2008年第3期42-44,共3页
Coal Science and Technology
关键词
井筒
破坏
治理
mine shaft
failure
repair