大规模定制中顺序间歇过程批调度研究

The batching scheduling problem for sequential batch process and some useful properties
下载PDF
导出
摘要 间歇过程生产在大规模定制中占有重要地位,顺序间歇过程是一种常见的间歇过程,现有研究将顺序间歇过程调度分为需求分批与批次调度两步求解过程,忽略了它们之间相互制约、不可分割的内在联系,为了校正这种人为断裂,以获得真正意义上的最优化调度,提出了顺序间歇过程批调度问题.用α | β | γ法对顺序间歇过程批调度问题进行描述,给出了基本的作业属性、加工环境和批调度性能指标.针对基于完成时间的性能指标,提出了两个并行机间歇过程批调度问题,在分析了几个有用性质后,将两个问题分别等价为固定费用运输问题和非线性运输问题.
机构地区 哈尔滨工业大学
出处 《机电产品开发与创新》 2005年第z1期51-54,57,共5页 Development & Innovation of Machinery & Electrical Products
  • 相关文献

参考文献16

  • 1[1]FLOUDAS, C.A., LIN, X.. Continuous-time versus discrete-time approaches for scheduling of chemical processes: a review [J]. Computers and Chemical Engineering, 2004, 28: 2109~2129.
  • 2[2]CERDA, J., HENNING, G. P., GROSSMANN, 1. E. A mixed-integer linear programming model for short-term scheduling of single-stage multiproduct batch plants with parallel lines [J]. Industrial and Engineering Chemistry Research,1997, 36(5): 1695~1707.
  • 3[3]MENDEZ, C.A., HENNING, G. P., CERDA, J. Optimal scheduling of batch plants satisfying multiple product orders with different due-dates [J]. Computers and Chemical Engineering, 2000, 24: 2223~2245.
  • 4[4]HUI, C., GUPTA, A. A bi-index continuous-time mixed-integer linear programming model for single-stage batch scheduling with parallel units [J].Industrial and Engineering Chemistry Research, 2001, 40(25): 5960~5967.
  • 5[5]CHEN, C.L., LIU, C.L., FENG, X.D., et al. Optimal short-term scheduling of multiproduct single-stage batch plants with parallel lines [J]. Industrial Engineering & Chemical Research, 2002, 41(5): 1249~1260.
  • 6[6]Ku, H.M., Karimi, L. Scheduling in serial multiproduct batch processes with due-date penalties [J]. Industrial Engineering & Chemical Research, 1990, 29:580~590.
  • 7[7]Ku, H.M., Karimi, I.. An evaluation of simulated annealing for batch process scheduling[J]. Industrial Engineering & Chemical Research, 1991, 30: 163~169.
  • 8[8]Kim, M., Jung, J.H., Lee, I.B.. Optimal scheduling of multiproduct batch processes for various intermediate storage policies [J]. Industrial Engineering & Chemical Research, 1996, 35: 4058~4066.
  • 9[9]Kim, M., Jung, J.H., Lee, I.B.. Optimal scheduling for a multiproduct batch process with minimization of penalty on due date period [J]. Industrial Engineering & Chemical Research, 2001, 40: 228~233.
  • 10[10]PINTO, J. M., GROSSMANN, I. E. A continuous time mixed integer linear programming model for short term scheduling of multistage batch plants [J].Industrial and Engineering Chemistry Research, 1995, 34(9): 3037~3051.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部