摘要
主要描述了控制系统的功能与系统设计、设备制造、控制系统仿真、现场调试等过程,总结了取得的经验和存在的问题。通过现场调试和实际运行表明:控制系统的参数在要求运行的范围内,系统设备运行良好,满足秦山核电二期工程的要求。它的建成为我国自主设计建造大型商用核电站反应堆控制系统积累了宝贵的工程经验。
This paper describes the function and design of the control system, equipment manufacture, simulation of control system and site commissioning, summaries the experiences gained and the problems occurred. The site commissioning and operation indicate that the parameters of control system are within the designated ranges, equipment runs well and the whole system satisfies the requirements of Qinshan Phase Ⅱ NPP Project. It provides valuable experiences for the indigenous design and manufacture of the reactor control system for large commercial NPPs.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2003年第z1期231-234,共4页
Nuclear Power Engineering
关键词
反应堆
控制系统
控制系统仿真
Reactor
Control system
Control system simulation