摘要 随着城网建设与改造的加快 ,城网配电自动化系统的实施建设 ,对 110kV变电所设计提出了新的要求。城市负荷增大、用地紧张、供电可靠性要求高等特点 ,使城网变电所设计面临诸多困难。本文从电源设置、主接线形式确定、设备选择和配电装置布置等方面提出了新的设计思路 ,指出了城网变电所小型室内化、无人值守综合自动化的发展方向 。 With the quickening development of urban network construction and upgradation, the introduction of urban network distribution automation system brings new requirements to design of 110 kV substation .The design task encounters such obstacles as urban load enlargement, building land insufficiency, higher electricity supply reliability, etc. The paper provides a new method of designing in terms of source allocation, busbar pattern determining, apparatus choosing and distribution device arrangement, etc. Further more, the paper points out that urban substations tend to be small sized, unattentive, comprehensively automatic.
作者 张秀芹
出处 《河北农业大学学报》 CAS CSCD 北大核心 2002年第z1期299-300,共2页 Journal of Hebei Agricultural University
关键词 城网建设与改造 变电所 自动化 设计 urban network construction and upgradation substations automation design
  • 相关文献

同被引文献4

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部