摘要
介绍了阳泉三矿裕公井副井提升机制动系统改造的基本情况。包括制动系统技术改造方案的比较,技术参数的确定,以及改造后的运行情况等。
This paper describes the basic situations of the transformation of hoist braking system in Yugong auxiliary shaft of No.3 Yangquan Mine, including the scheme comparison, the determination of technical parameters as well as its operation after transformation.
出处
《矿业安全与环保》
2001年第z1期127-128,130,共3页
Mining Safety & Environmental Protection