摘要
在 1998年审定的莱城电厂国产引进型2×300MW机组初设的基础上,按照21世纪示范电厂的模型在主厂房布置、设备及材料选择及提高管理和控制自动化水平等方面进行了优化设计,降低工程造价4938万元。
On the base of the former preliminary design of the domestic 2 ×300Mwunits with the imported techn- ology for shandong laicheng Power Plant. The main building layout the delection of equipment and mate- rial as well as the improvement and control automa- tion leveletc. have been optimized and then this project cost is reduced by 49. 38 million Yuan in ac- cordance with the model of Twenty-First century Example Power Plant.
出处
《山东电力高等专科学校学报》
2001年第2期11-14,共4页
Journal of Shandong Electric Power College
关键词
优化设计
经济效益
静态投资
optimiging design economic efficiency static in- vestment