摘要 根据核电厂内部结构维修的特殊性,研制了一套局部干法自动水下焊接实验系统,进行了15 m水深局部干法自动水下坡口对接焊实验,并采用集成汉诺威弧焊质量分析仪对自动水下焊接的工艺过程进行分析.结果表明,焊缝成型良好,能够满足相关执行标准的要求,为核电站堆内构件在役维修技术的发展奠定了基础. According to the particularity of nuclear power plant internal structure repair,this paper developed a set of local dry automatic underwater welding test system.It did the experiment of 15 meters water depth groove butt automatic welding and used integrated Hannover arc welding analyser to analyze the welding technological process. The examination results show that the welded formation is good and can satisfy related standard request.This lays the foundation for nuclear power station in service repair.
出处 《上海交通大学学报》 EI CAS CSCD 北大核心 2008年第S1期126-128,共3页 Journal of Shanghai Jiaotong University
基金 国家“863”计划资助项目(2006AA09Z329) 国防科工委资助项目(5K201) 北京石油化工学院青年科研基金资助项目(N07-18)
关键词 核电 自动水下焊接 汉诺威分析仪 熔滴过渡 nuclear power automatic underwater welding Hannover analyser metal transfer
  • 相关文献

参考文献2

二级参考文献2

  • 1王宝.药芯焊丝CO2气体保护焊电参数[A]..2003汽车焊接国际论坛论文集[C].,2003,11.183-186.
  • 2DietrichRehfeldt.Computer-aided quality assurance(CAQ) of A1-MIG welding with analysator hannover[A]..2003汽车焊接国际论坛论文集[C].,2003,11.39-50.

共引文献9

同被引文献33

引证文献6

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部