摘要
钢框架-核心筒结构在施工过程中,由于钢结构安装和土建施工相互制约,致使整体施工进度滞后。通过改变节点设计及采用多功能爬架施工大大缩短了施工工期。
Because the steel structure installment and the construction restrict mutually,steel frame-core tube structure in construction process causes the whole construction process lag. By design of the change node and use of multifunctional climbing-frame,the construction time is reduced greatly.