芭蕉河一级水电站1台机组启动试验时发生事故,有块钢板进入转轮室,介绍事故损失情况及汲取教训,启动试验必须做好各项检查,确保启动安全。
Once when the 1 000 kW hydro-generating set of Bajiaohe-I Hydropower Station started up several minutes later,a piece of steel plate was drawn into the runner chamber and caused the generating set shut down.A deep lesson is drawn from this accident,the repair of the damaged components has completed.
出处
《湖北水力发电》
2009年第2期58-59,共2页
Hubei Water Power
关键词
芭蕉河一级电站
机组启动事故
Bajiaohe-Ⅰ Hydropower Station
accident of hydro-generating set