基于业主视角的多模式项目支付进度问题及其启发式算法 被引量:1

Client perspective based multi-mode project payment scheduling problem and its heuristic
原文传递
导出
摘要 从业主的视角研究了活动具有多种执行模式的项目支付进度问题.首先对所研究问题进行界定并定义文中所用到的符号;随后构建业主视角多模式项目支付进度问题的优化模型,通过将其转化为离散时间/费用权衡问题的子问题P_C|T,证明该问题为强NP-hard;基于这一结果,针对问题特征设计启发式求解算法,通过在两个模块之间的模拟退火搜索迭代,获得其满意解;在40个随机生成的标准算例上对算法进行测试,得到如下结论:算法可以在24.63秒内求解所有的算例,满意解对应的目标函数值与其上界的相对偏差不超过8.24%;随着支付次数、折现率、承包商可接受最低利润率及支付比例的上升,业主的项目净现值下降. This paper involves the multi-mode project payment scheduling problem from the client perspective. The problem is identified and the notations are defined at first.Then the optimization model of the problem is constructed and its strong NP-hardness is proved by simplifying it to P_C|T in the discrete time/cost tradeoff problem.Based on the characteristics of the problem,a special heuristic composed of two modules is developed.Through the iteration between the two modules,the heuristic can find the desirable...
出处 《系统工程理论与实践》 EI CSCD 北大核心 2009年第2期70-77,共8页 Systems Engineering-Theory & Practice
基金 国家自然科学基金(70673077) 国家社会科学基金(07XJL002) 陕西省软科学研究项目(2007KR56)
关键词 支付进度安排 活动执行模式 业主视角 优化模型 启发式算法 project payment scheduling performing mode of activity client s perspective optimal model heuristic
  • 相关文献

参考文献1

  • 1Nalini Dayanand,Rema Padman. A Two Stage Search Heuristic for Scheduling Payments in Projects[J] 2001,Annals of Operations Research(1-4):197~220

同被引文献10

  • 1Dayanand N, Padman R. On modeling progress payments in project networks[J]. Journal of the Operational Research Society, 1997, 48(9): 906-918.
  • 2Dayanand N, Padman R. Project contracts and payments schedules: The client's problem[J]. Management Science, 2001, 47(12): 1654- 1667.
  • 3Dayanand N, Padman R. A two stage search heuristic for scheduling payments in projects[J]. Annals of Operation Research, 2001, 102(1): 197-220.
  • 4Ulusoy G, Cebelli S. An equitable approach to the payment scheduling problem in project management[J]. European Journal of Operational Research, 2000, 127(2): 262-278.
  • 5Kavlak N, Ulusoy G, Serifoglu F S, et al. Cfient-contractor bargaining on net present value in project scheduling with limited resources[J]. Naval Research Logistics, 2009, 56(2): 93-112.
  • 6Szmereskovsky J G. The impact of contractor behaviour on the client's payment scheduling problem[J]. Management Science, 2005, 51(4): 629--640.
  • 7He Z, Wang N, Jia T, et al. Simulated annealing and tabu search for multi-mode project payment scheduling[J]. European Journal of Operational Research, 2009, 198(3): 688-696.
  • 8Waligora G. Discrete-continuous project scheduling with discounted cash flows: A tabu search approach[J]. Computers and Opera- tions Research, 2008, 35(7): 2141-2153.
  • 9Kolisch R, Sprecher A. PSPLIB: A project scheduling problem library[J]. European Journal of Operational Research, 1996, 96(1): 205-216.
  • 10何正文,徐渝.多模式项目支付进度安排的优化模型及求解[J].系统工程学报,2007,22(5):474-479. 被引量:6

引证文献1

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部