摘要
从施工工艺及施工过程中的要点等方面对预应力高强混凝土管桩在高层建筑基础处理中应用进行了论述,阐明了这种桩型的基础处理方法无污染、噪音小和造价适中的优点.
The prestressing force high intensity concrete tubular pipe pole is discussed in the aspect of construction technology and construction points concerning its application in the base construction of high-rises.The advantages of this processing method of the concrete tubular pile are pollution-free,low noise and moderate cost of construction.
出处
《湖北工业大学学报》
2009年第2期94-96,共3页
Journal of Hubei University of Technology
关键词
预应力
混凝土管桩
高层建筑
地基处理
prestressing force
concrete tubular pile
high building
foundation process