摘要
溧阳市110 kV变电所是全市首座全户内型变电所,通过实地观测法对变电所进行沉降观测,分析影响变电所安全运行的因素,对溧阳市110 kV变电所的正常使用具有非常重要的意义。
110 kV Liyang Substation are the city s first all-indoor-type substation,through field observation method for settlement of the substation observation,analysis of the impact the safe operation of substation factors,on the 110 kV Liyang Substation the normal use of great significance.
出处
《太原科技》
2009年第4期39-40,43,共3页
Taiyuan Science and Technology
关键词
110
KV变电所
沉降观测
沉降数据
溧阳市
110 kV electric substation
settlement observation
settlement data
Liyang city