摘要
重庆大佛寺长江大桥为一座主跨 450 m的预应力混凝土斜拉桥 ,介绍了该桥主塔墩嵌固式承台大体积混凝土施工 ,分析了混凝土裂缝产生的机理 ,提出了防止温度裂缝产生的监控措施。
Chongqing Dafusi Changjiang River Bridge is a PC cable\|stayed bridge with a main span of 450 m.Construction of massive concrete of the built\|in pylon base of the bridge is described. The mechanism of crazing of the concrete is analyzed, and monitoring measures against the crazing due to temperatures are proposed.
出处
《桥梁建设》
EI
CSCD
北大核心
2000年第2期32-35,共4页
Bridge Construction
关键词
斜拉桥
承台
混凝土灌注
温度监测
裂缝
温度应力
cable\|stayed bridge, pylon base, concrete placing, temperature monitoring, crazing, temperature stress